E.ON Ruhrgasleitung Lauterbach Project.

Project description

This project was characterized by ist short-term nature and consequently the high flexibility we needed. The whole project last one month.

Scope of work

Installation of cable cranes and operation, transport of pipes and fitting into welding position in steep area, transport of Sandbags, blasting and coating material, padding and backfilling material.

Project Info

Customer: Nacap GmbH
Project owner: e.on
Location: Germany
Date: 2007

Technical details

Total length: 600 m
Towers: 2
Payload: 10.5 to
Total volume: 600 m pipes, 1.000 to sand
Duration of project: 1 month
Size of pipes: 42” / approx. 107 cm
Slope: up to 42°
Machinery in usage: 2 carriages SFM 30/60, 1 winch GANTNER HSW 130

Project Gallery

Why cable cranes?

Discover the numerous advantages of cable crane systems!

LONGTIME EXPERIENCE IN DEVELOPING AND EXECUTING TRANSPORTATION PROJECTS.

LCS Cable Cranes has been carrying out many challenging projects all over the world addressing new challenges and geographical and meteorological circumstances and could always meet them to the fullest customer satisfaction.
Our cable crane systems have been used for a large construction variety.

Visit a selection of our successful projects