E.ON Ruhrgasleitung Lauterbach Project.

Project description
This project was characterized by ist short-term nature and consequently the high flexibility we needed. The whole project last one month.
Scope of work
Installation of cable cranes and operation, transport of pipes and fitting into welding position in steep area, transport of Sandbags, blasting and coating material, padding and backfilling material.
Project Info
Customer: Nacap GmbH
Project owner: e.on
Location: Germany
Date: 2007
Technical details
Total length: 600 m
Towers: 2
Payload: 10.5 to
Total volume: 600 m pipes, 1.000 to sand
Duration of project: 1 month
Size of pipes: 42” / approx. 107 cm
Slope: up to 42°
Machinery in usage: 2 carriages SFM 30/60, 1 winch GANTNER HSW 130