Zawtika Onshore Pipeline.

Project 01 description

At our first project for the Zawtika Pipeline Project in Myanmar, we installed a cable crane system at 5 different locations for the laying of the pipeline. LCS operated with spider-excavators and was resposible for the trenching.

Scope of work

Installation of cable cranes and operation, trenching with special equipment, transport of pipes and fitting into welding position, transport of Sandbags, blasting and coating material, padding and backfilling work

Project Info

Customer: China Petroleum Pipeline
Project Owner: ATL (PTTEPI and MOGE)
Location: Myanmar
Date: 2012 – 2013

Technical details

Number of cranes: 1
Locations: 5
Length: 5,000 m
Towers: up to 8
Payload: 8 to
Transported goods: Pipes, padding material, sandbag, blasting and coating equipment
Excavators: used for terrain and trenching work in very steep areas up to 60°
Duration of project: 8 months
Size if the pipes: 28” / approx. 71 cm
Slope: up to 50°
Used machinery: 4 Carriage SFM 30/60; Winch Gantner GW 350D, 2 spider excavators S1

Project 01 Gallery

Project 02 description

For the Zawtika Pipeline project, LCS acted for the first time as full Service Pipeline construction company, constructing the entire pipeline at special points. We were in charge of the complete process-chain: starting from the logistics (beginning at the harbor) to the preparation of the terrain with Spider excavators and the installation and padding work in the difficult terrain, where the pipelines must be installed.

Scope of work

Pipeline construction at RR2 and RR4 special points; Complete pipeline work including Installation of cable cranes and operation, transport of pipes and fitting into welding position, welding, erosion control, padding and backfilling, reinstatement.

Project Info

Customer/Project owner: ATL (PTTEPI and MOGE)
Location: Myanmar
Date: 2013 – 2014

Technical details

Number of cranes: 1
Length: 5,200 m and 800 m
Payload: 8 to
Transported goods: Pipes, padding material, sandbag, blasting and coating equipment
Excavators: used for terrain and trenching work in very steep areas up to 60°
Duration of project: 4 months
Size if the pipes: 28” / approx. 71 cm
Slope: up to 48°
Used machinery: 4 Carriage SFM 30/60; Winch GANTNER GW 350D, Winch GANTNER HSW 130/260, spider excavators S1

Project 02 Gallery

Why cable cranes?

Discover the numerous advantages of cable crane systems!

LONGTIME EXPERIENCE IN DEVELOPING AND EXECUTING TRANSPORTATION PROJECTS.

LCS Cable Cranes has been carrying out many challenging projects all over the world addressing new challenges and geographical and meteorological circumstances and could always meet them to the fullest customer satisfaction.