Zawtika Onshore Pipeline.

Project 01 description
At our first project for the Zawtika Pipeline Project in Myanmar, we installed a cable crane system at 5 different locations for the laying of the pipeline. LCS operated with spider-excavators and was resposible for the trenching.
Scope of work
Installation of cable cranes and operation, trenching with special equipment, transport of pipes and fitting into welding position, transport of Sandbags, blasting and coating material, padding and backfilling work
Project Info
Customer: China Petroleum Pipeline
Project Owner: ATL (PTTEPI and MOGE)
Location: Myanmar
Date: 2012 – 2013
Technical details
Number of cranes: 1
Locations: 5
Length: 5,000 m
Towers: up to 8
Payload: 8 to
Transported goods: Pipes, padding material, sandbag, blasting and coating equipment
Excavators: used for terrain and trenching work in very steep areas up to 60°
Duration of project: 8 months
Size if the pipes: 28” / approx. 71 cm
Slope: up to 50°
Used machinery: 4 Carriage SFM 30/60; Winch Gantner GW 350D, 2 spider excavators S1
Project 01 Gallery
Project 02 description
For the Zawtika Pipeline project, LCS acted for the first time as full Service Pipeline construction company, constructing the entire pipeline at special points. We were in charge of the complete process-chain: starting from the logistics (beginning at the harbor) to the preparation of the terrain with Spider excavators and the installation and padding work in the difficult terrain, where the pipelines must be installed.
Scope of work
Pipeline construction at RR2 and RR4 special points; Complete pipeline work including Installation of cable cranes and operation, transport of pipes and fitting into welding position, welding, erosion control, padding and backfilling, reinstatement.
Project Info
Customer/Project owner: ATL (PTTEPI and MOGE)
Location: Myanmar
Date: 2013 – 2014
Technical details
Number of cranes: 1
Length: 5,200 m and 800 m
Payload: 8 to
Transported goods: Pipes, padding material, sandbag, blasting and coating equipment
Excavators: used for terrain and trenching work in very steep areas up to 60°
Duration of project: 4 months
Size if the pipes: 28” / approx. 71 cm
Slope: up to 48°
Used machinery: 4 Carriage SFM 30/60; Winch GANTNER GW 350D, Winch GANTNER HSW 130/260, spider excavators S1