Chile

Installation of a 13-ton cable crane system as part of a large-scale seawater desalination project in Northern Chile

This project makes a significant contribution toward achieving the goal of reducing water consumption in mining production by 60% by 2030, thereby promoting sustainable development.

To supply three major mining operations in northern Chile with desalinated water, the construction of a desalination plant and a water collection and pumping system is required. The installation of the necessary pipelines in the steep and demanding hillside terrain of Tocopilla is being carried out using a cable crane system with horizontal bends (curves) from LCS Cable Cranes, with a load capacity of 13 tons and a length of approximately 1.6 kilometers.

This solution was specifically tailored to the challenging terrain and logistical conditions on-site. It consists of six towers – including two curve towers – and adapts optimally to the complex terrain profile. The new GW501 winch system and the powerful GC200 crane unit are used to ensure precise and reliable material transport along the steep route.

Close On-site Collaboration

LCS installation specialists were on-site for several weeks. In close cooperation with the client’s local workforce, the system was successfully installed under challenging conditions. The operation of the cable crane system is also supervised by an LCS team on-site to ensure smooth material transport operations.

Commissioning and Project Progress

The installation work was completed at the end of May 2025. Since then, the system has been in active operation – until the entire pipeline has been laid. Once these works are complete, the cable crane system will be professionally dismantled by the LCS assembly team and returned to Austria.

Project Details

Client

Techint Engineering & Construction

Project Owner

Codelco

Location

Chile

Year

2025

Keyfacts

TOTAL LENGTH

1.6 km

Slope

up to 35 %

payload

13 t

MAX. ROPE SPEED

3 m / sec.

PIPE DIAMETER

48 "

NUMBER OF TOWERS

6, 2 of them with curves

loads

pipelines, construction material, construction equipment and personnel transportation

Projects

LCS in action